Expediting

Production and procurement expediting

Material ordered, received and in production on the dates the schedule needs. Verified on the shop floor, reported with forecast dates.

01What the service involves

Production expediting tracks an order from purchase order acknowledgement to shipment readiness. QUALITAS TR verifies that the supplier has placed orders for raw materials and bought-out items, follows their delivery, confirms material receipt and inspection, and tracks manufacturing progress operation by operation against the schedule.

Procurement expediting extends to the supplier's sub-suppliers: castings, forgings, motors, instruments, valves and other long lead items are followed directly where they determine the critical path.

02Why buyers need it

Most delivery delays start in procurement: materials ordered late, sub-supplier slots missed, bought-out items with long lead times not identified. Production expediting detects these early, while there is still float to recover.

Verified progress also gives you defensible information for your own customers and project schedules.

03Typical applications

  • Engineered equipment with long lead items
  • Castings and forgings with pattern and tooling stages
  • Fabricated equipment with sub-supplier content
  • Spare parts programmes
  • Framework agreements with many orders
  • Critical path items on capital projects

04Methodology

  1. Expediting plan

    Order criticality, milestones, sub-supplier list and visit frequency defined.

  2. Procurement check

    Sub-orders placed, confirmed and delivered on time.

  3. Manufacturing check

    Routing, machine loading and work in progress verified.

  4. Forecast

    Each milestone forecast with confidence and cause of variance.

  5. Escalation

    Delays escalated with recovery actions and follow-up.

Expediting dashboard: planned versus actual progress

Weighted manufacturing progress of a fabricated equipment order with milestone markers. Select a scenario or a milestone.

Illustrative data

Expediting compares verified physical progress with the agreed schedule and flags delivery risk early.

05Applicable standards and references

Expediting follows project management good practice. Milestones and reporting are aligned with your project control system.

06Deliverables

  • Expediting plan
  • Field expediting reports with photographs
  • Long lead item tracker
  • Milestone forecast table
  • Escalation log

07Customer benefits

  • Delivery risks visible early
  • Sub-supplier delays caught
  • Defensible forecasts
  • Reduced firefighting
  • Better on-time delivery

08How QUALITAS TR supports you

The expediting dashboard below shows how planned and verified progress are compared and when escalation is triggered.

Direct contact. No forms.

Discuss your inspection, audit or project requirements

Send us the purchase order scope, drawings, specifications or ITP and the supplier location. You will receive a written proposal with scope, inspector profile, schedule and reporting format.

Email[email protected] Telephone+90 533 197 19 81
OfficeBeştepe Mah. Nergiz Sok. 7/2 Kat:3 No: 87, Yenimahalle, Ankara, Turkey