Supplier Inspection and Production Surveillance
Source and shop inspection during manufacturing: raw material, in-process and final inspection, and production surveillance.
Service portfolio
Ten connected service families covering the complete industrial quality and project lifecycle, from supplier selection to delivery.
All servicesIndustries
Sector-specific inspection and supplier quality support across Turkish manufacturing.
All industriesInspection methods
How each inspection and testing method works, where it applies and what it cannot detect.
All methodsStandards library
Plain-language guides to the standards our inspections and audits refer to.
All standardsKnowledge center
Technical guides, quality tools and calculators for quality, supplier and project teams.
Knowledge centerService family 02
Independent inspectors at your supplier's facility, verifying conformity at the stages that matter and reporting facts you can act on.
Overview
Third-party inspection, also called vendor, source or shop inspection, places an independent inspector at the manufacturer's premises to verify that purchased goods meet the purchase order, drawings, specifications and applicable codes before they leave the factory.
QUALITAS TR covers the full range of manufacturing inspection, from raw material and in-process checks through final and pre-shipment inspection to container loading. Inspections can be single visits, a programme of visits linked to an ITP, or continuous surveillance for critical orders.
Our inspectors have engineering backgrounds in metallurgy, mechanical manufacturing and quality engineering. They read drawings and specifications, understand how the part is made and recognise early signs of a problem, which is what separates useful inspection from box ticking.
Each service page explains scope, methodology, standards and deliverables.
Source and shop inspection during manufacturing: raw material, in-process and final inspection, and production surveillance.
Dimensional, GD&T and drawing compliance verification, CMM witnessing, laser measurement coordination and first article layouts.
Inspection of rotating and static mechanical equipment: assembly, hardness, mechanical, load, pressure, leak and running tests.
Inspection of electrical panels, switchgear, cables, instrumentation and control systems, with electrical test witnessing.
Final random or complete inspection of finished goods before shipment: quantity, conformity, workmanship, packing and marking.
Export packaging, preservation, marking and container condition checks and supervision of loading and securing.
Inspection activities grouped by discipline. Scope is always set by your purchase order, ITP or inspection instruction.
Hold, witness and review points give the buyer control without stopping the supplier's work unnecessarily.
A typical ITP sequence for a fabricated and machined assembly.
| # | Activity | Reference | Supplier | Third party | Record |
|---|---|---|---|---|---|
| 1 | Pre-inspection meeting, ITP and drawing revision check | PO, specification | P | H | Minutes |
| 2 | Material certificate review and identification | EN 10204 3.1 | P | R | MTC log |
| 3 | WPS, PQR and welder qualification review | ISO 15614, ISO 9606 | P | R | Review sheet |
| 4 | Fit-up and in-process weld visual inspection | ISO 17637, ISO 5817 | P | W | Weld map |
| 5 | NDT after final heat treatment | Project NDT procedure | P | W | NDT reports |
| 6 | Final dimensional inspection | Drawing, GD&T | P | H | Dimensional report |
| 7 | Pressure or functional test | Test procedure | P | H | Test certificate |
| 8 | Coating DFT, marking, packing and release | Coating spec, packing spec | P | H | Release note |
How we work
Every visit follows the same disciplined sequence, so reports are comparable across suppliers and orders.
We confirm scope, documents, acceptance criteria, sampling and the latest drawing revisions before travelling.
Date, readiness and access are confirmed with the supplier. Partial readiness is reported, not hidden.
Documents, material, dimensions, workmanship, testing and marking are checked against the agreed criteria with photographs and measured values.
Deviations are discussed with the supplier on site and classified as critical, major or minor.
A structured report with a clear verdict: accepted, accepted with remarks, or rejected, issued within the agreed time.
Industries
Connected services
No. QUALITAS TR provides independent second- and third-party inspection on behalf of buyers. Where a regulation or contract requires an inspection body accredited to ISO/IEC 17020 or a notified body, we tell you and coordinate with such an organisation.
For locations in central Anatolia a visit can often be arranged within one to three working days. Other regions depend on travel. Tell us the date and city and we confirm availability by return.
Direct contact. No forms.
Send us the purchase order scope, drawings, specifications or ITP and the supplier location. You will receive a written proposal with scope, inspector profile, schedule and reporting format.