01What the service involves

QUALITAS TR inspects low voltage panels and switchgear, motor control centres, control and automation panels, cable and wiring, instrumentation and electrical equipment integrated into machinery and skids.

Inspection covers bill of materials and component conformity, enclosure and IP rating features, busbar and cable sizing against drawings, wiring quality and termination, labelling and ferrules, earthing and bonding, and the witnessing of routine tests such as insulation resistance, dielectric tests, continuity, functional and sequence tests.

02Why buyers need it

Electrical panels are often built from approved drawings but with substituted components, undocumented wiring changes or incomplete labelling. These issues delay commissioning and create safety risks.

Inspection at the panel builder, before cables are terminated in the field, is the most efficient point to correct them.

03Typical applications

  • Low voltage switchboards and MCCs
  • PLC and automation panels
  • Machine electrical equipment
  • Instrumentation on skids and packages
  • Cable and wiring harnesses
  • Renewable energy electrical equipment

04Methodology

  1. Document review

    Single line diagrams, schematics, BOM and test procedure reviewed.

  2. Construction check

    Enclosure, component brands and ratings, busbars, segregation and earthing verified.

  3. Wiring check

    Termination quality, cable sizes, colours, ferrules and labelling inspected.

  4. Test witnessing

    Insulation, dielectric, continuity, functional and sequence tests witnessed.

  5. Release

    Punch list closed, documents verified, release recommendation issued.

05Applicable standards and references

Panel assemblies are commonly built and tested to the IEC 61439 series and machinery electrical equipment to IEC 60204-1. Exact routine verification requirements are taken from the standard and edition named in your specification.

06Deliverables

  • Electrical inspection checklist and report
  • Test witnessing records
  • Component substitution list
  • Punch list
  • Release note

07Customer benefits

  • Fewer commissioning delays
  • Verified component conformity
  • Complete and correct labelling
  • Safer installations
  • Test evidence before shipment

08How QUALITAS TR supports you

Electrical inspections are planned together with mechanical inspection and FAT when panels are part of a machine or package, so one visit covers the complete unit.

Direct contact. No forms.

Discuss your inspection, audit or project requirements

Send us the purchase order scope, drawings, specifications or ITP and the supplier location. You will receive a written proposal with scope, inspector profile, schedule and reporting format.

Email[email protected] Telephone+90 533 197 19 81
OfficeBeştepe Mah. Nergiz Sok. 7/2 Kat:3 No: 87, Yenimahalle, Ankara, Turkey